Emirates Buildings are based in Abu Dhabi,
United Arab Emirates.
Emirates Buildings is a private shareholding company. One of our major investments is the E.V.G. - (Austria) 3D Construction Panel.
More... |
|
View the production stages of the 3D panels.
The E.V.G. 3D Construction Panel is detailed in the following processes:
1. Raw wire being reeled in preparation for...
2. Galvanised wires being welding into grid...
3. Galvanised Mesh is rolled in preparation...
More...
|
|
|
|
|
|
|
|
 |
|
|
200 Low Cost Houses at Al-Mafraq-Abu Dhabi
A combination of 5 & 4 bed rooms double storey villas along with an independent kitchen/servant block
Client:President Office – Private Department
Duration: 6 months -(September 1999 to February 2000)
Total Built-up Area : 63,000 M²pervilla
Total Project Value : 90,580,000 Dhs |
|
|
200 Low cost Houses at Khalifa City ‘B’-Abu Dhabi
5 bed Room Double Storey villas along with an independent kitchen/servant block
Client:
Works Department
Consultant:
Arab Consultants
Duration:
10 months-(September 2000 to June 2001)
Total Built-up Area :
69,000 M² per villa
Total Project Value :
170,000,000 Dhs
|
|
|
200 Low Cost Houses at Al Samha ‘East’- Abu Dhabi
6 bed Room Double Storey villas along with an attached kitchen/servant block
Client:
Abu Dhabi Municipality
Consultant:
International Engineering Centre
Duration:
10 months -(February 2001 to December 2001)
Total Built-up Area :
69,000 M² per villa
Total Project Value :
170,000,000 Dhs
|
|
|
204 Houses at Al HeeleiaAbu Dhabi
5 bed Room Double Storey villas along with an independent Majlis,kitchen and servant quarter
Client:
Abu Dhabi Municipality
Consultant:
Al Yasat
Duration:
18 months-(June 2002 – Ongoing)
Total Built-up Area :
99,144 M² per villa
Total Project Value :
98,940,000 Dhs
|
|
|
|
Construction of Guest Villa & Health Club at Al- Aryam Island,Abu Dhabi
Single storey Building with swimming-Pool ,Sauna ,Steam Room…etc
Client:
H.H.SH.HAMDAN BIN ZAYED AL NAHYAN
Consultant:
Golden Bell
Duration:
5 months -(September 2003 – October 2004)
Total Built-up Area :
1200 M²
Total Project Value :
12,498,673 Dhs
|
|
|
Noncommissioned Officer Accommodation (Phase 3) at AL MUROOR RoadAbu Dhabi
Ground + 1 Building
Client:
Ministry of Public Works & Housing Building Dept Consultant:
Golden Bell
Consultant:
Al Burj Consultants
Duration :
12 months-(JANUARY 2004 –JANUARY 2005)
Total Built-up Area :
910 M²
Total Project Value :
2,698,633 Dhs
|
|
|
Two villas at SHAHAMA at Abu Dhabi
Client:
DEFENCE PROJECT
Location:
SHAHAMA ABU DHABI
|
|
|
OYOUN Village at AL AIN
TOWNSHIP WITH 148 VILLAS CLUB HOUSE,SWIMMING POOLS, GUARD ROOM..etc
Client:
AL RAYAN Investments Consultant:
EWAN ENGG.Consultants
Duration:
16 months
Project Manger :
Projacs
Total Built-up Area :
84,000 M²
Total Project Value :
66,991,611 Dhs
|
|
|
|
|
|  |
|
 |
|
200 Low Cost Houses at Al Samha East
6 Bedroom double storey villas along with an attached kitchen/servant block.
Client: Abu Dhabi Municipality
Duration: 10 Months (02/01 - 12/01)
Floor Area: 395 sq.m
More... |
|
|
|
|
|